
www.JacksonControl.com

www.JacksonControl.com

www.JacksonControl.com

www.JacksonControl.com

www.JacksonControl.com

www.JacksonControl.com

www.JacksonControl.com

www.JacksonControl.com

www.JacksonControl.com

www.JacksonControl.com

www.JacksonControl.com

www.JacksonControl.com

www.JacksonControl.com

www.JacksonControl.com

www.JacksonControl.com

www.JacksonControl.com

www.JacksonControl.com

www.JacksonControl.com

www.JacksonControl.com

www.JacksonControl.com

www.JacksonControl.com
The "Last 5% Never Done" SyndromePerhaps the most persistent challenge in higher education commissioning is the tendency for the final 5% of commissioning activities to remain incomplete as projects rush to meet occupancy deadlines. This phenomenon must be explicitly acknowledged and addressed through contractual requirements, financial holdbacks, and clear completion criteria.

www.JacksonControl.com

www.JacksonControl.com

www.JacksonControl.com

www.JacksonControl.com

www.JacksonControl.com

www.JacksonControl.com
PROJECT NAME: ________________________________
PROJECT NUMBER: ______________________________
DATE SUBMITTED: ______________________________
CONTROLS CONTRACTOR: _________________________
IT REPRESENTATIVE: ____________________________
== REQUIRED DOCUMENTATION CHECKLIST ==
□ Network diagram (with BACnet/IP routing)
□ Port/protocol matrix + firewall requirements
□ VLAN assignments and NAC policies
□ Time sync source/method
□ Certificate management plan
□ BACnet/SC readiness statement
== NETWORK DIAGRAM REQUIREMENTS ==
The network diagram must include:
1. All supervisory controllers with IP addresses
2. All field controllers/device networks
3. All BACnet/IP routing paths
4. Connections to campus networks
5. Firewalls and security boundaries
6. Required ports for each connection
7. Any cloud connections or remote access

www.JacksonControl.com
== PORT/PROTOCOL MATRIX ==
| Source | Destination | Protocol | Port | Purpose |
|---------------|---------------|----------|------|-------------------|
| [Example] | [Example] | [Ex] | [Ex] | [Example] |
| BAS Server | Field Network | BACnet/IP| 47808| Device Communication|
| Remote Access | BAS Server | HTTPS | 443 | Secure Web Access |
| [Add rows as needed for all required communication paths]
== VLAN ASSIGNMENTS AND NAC POLICIES ==
VLAN Name: ____________________________
VLAN Number: __________________________
Subnet: _______________________________
Default Gateway: _______________________
DHCP Range (if applicable): ____________
Static IP Range: _______________________
NAC Authentication Method: _____________
Device Registration Process: ___________
== TIME SYNCHRONIZATION ==
Primary Time Source: ___________________
Backup Time Source: ___________________
Synchronization Method: _______________
Synchronization Interval: _____________
Time Zone Configuration: ______________
== CERTIFICATE MANAGEMENT ==
Certificate Authority: ________________
Certificate Type: ____________________
Certificate Issuance Process: ________
Certificate Renewal Process: _________
Certificate Distribution Method: ______

www.JacksonControl.com
== BACnet/SC READINESS ==
□ BACnet/SC will be implemented
□ BACnet/SC will NOT be implemented (explain): _______________________
If implementing BACnet/SC:
Hub Configuration: ___________________
Security Policies: ___________________
Key Management Approach: _____________
== APPROVALS ==
Controls Contractor Representative:
Name: ______________________________
Signature: _________________________ Date: __________
IT Department Representative:
Name: ______________________________
Signature: _________________________ Date: __________
Commissioning Provider:
Name: ______________________________
Signature: _________________________ Date: __________
Owner's Representative:
Name: ______________________________
Signature: _________________________ Date: __________

www.JacksonControl.com

www.JacksonControl.com

www.JacksonControl.com

www.JacksonControl.com

www.JacksonControl.com

www.JacksonControl.com

www.JacksonControl.com
Performance criteria shall be expressed as measurable setpoints, tolerances, and modes tied to BAS points. Acceptance requires trend exports demonstrating criteria over defined conditions. Vague requirements such as 'energy efficient operation' or 'occupant comfort' must be translated into specific, measurable parameters with clear acceptance thresholds. The OPR shall include a matrix of acceptance criteria that defines the specific evidence required to verify each performance requirement.
Controls contractor shall submit sequence of operation (SOO) aligned to drawings/specifications, complete points list with I/O mapping, alarm priority matrix with response protocols, minimum trend plan specifying points, intervals, and duration, and draft functional performance test (FPT) scripts with pass/fail criteria. Submittals missing any of these elements will be rejected as incomplete. The controls submittal must be approved before any control system hardware is ordered or installed.
Provide network diagram showing all controllers and communication paths, port/protocol matrix detailing all required network communications, time synchronization source and method, VLAN/NAC requirements, certificate management plan, and BACnet/SC readiness statement. Obtain owner IT department sign-off on this complete package before any device installation. Any changes to the approved IT configuration must be documented and resubmitted for approval before implementation.

www.JacksonControl.com
Identify clear authority for setpoints, valve positions, and calibration values where TAB and controls responsibilities overlap. The Commissioning Provider shall witness both control system start-up and TAB procedures to ensure coordination. Functional performance testing shall commence only upon acceptance of the final TAB report for each system. All field adjustments shall be documented in both TAB and controls documentation. Graphics shall be verified to accurately reflect field conditions before system acceptance.
Include placeholder schedule and method for seasonal testing when full-load conditions cannot be achieved at the time of initial commissioning. Provide detailed integrated systems test plan for all life-safety interactions (e.g., smoke control, emergency power response) and coordinate testing procedures with the Authority Having Jurisdiction (AHJ). Budget and planning documents shall include provisions for commissioning activities that extend beyond substantial completion to verify seasonal performance.
Configure trend logs for all points necessary to verify sequences of operation and performance criteria. Trend data shall be collected at intervals appropriate to the system dynamics (typically 5-15 minutes for most HVAC applications) and for durations sufficient to demonstrate stable operation (minimum 24 hours for basic functions, up to one week for weather-dependent functions). Trend data shall be provided in a format that allows for analysis by the commissioning team and shall be included in the final commissioning documentation.

www.JacksonControl.com
Training and Knowledge TransferProvide comprehensive training on control system operation, maintenance, and troubleshooting. Training shall include hands-on sessions with the actual installed systems, recorded video documentation for future reference, detailed system manuals, and checklists for common operational tasks. Training shall be provided in multiple sessions to accommodate different staff schedules and shall include follow-up sessions after the system has been in operation for at least 30 days to address questions that arise during initial operation.
Provide complete as-built documentation including updated sequences of operation, point lists, network diagrams, programming code (where applicable), and user interface screenshots. Documentation shall be provided in both electronic and printed formats, organized in a logical manner that facilitates troubleshooting and maintenance. Electronic documentation shall be provided in non-proprietary formats (PDF, Excel, etc.) that do not require special software to access.

www.JacksonControl.com
System/Project: _______________________________________
What happened: _______________________________________
_____________________________________________________
_____________________________________________________
When in the project it occurred: _______________________
Impact on schedule/performance: _______________________
_____________________________________________________

www.JacksonControl.com
_____________________________________________________
_____________________________________________________
_____________________________________________________
_____________________________________________________

www.JacksonControl.com
_____________________________________________________
_____________________________________________________
_____________________________________________________
_____________________________________________________

www.JacksonControl.com

www.JacksonControl.com

www.JacksonControl.com

www.JacksonControl.com

www.JacksonControl.com

www.JacksonControl.com

www.JacksonControl.com

www.JacksonControl.com

www.JacksonControl.com

www.JacksonControl.com